Joel Ssenyonyi, who is COSASE chairperson and Nakawa West MP, and the other committee members including Mpindi, Alex Ruhunda of Fort Portal Central Division questioned UCAA officials about the absence of rumps at the existing passenger terminal buildings and also the modified building that will be an extension for the current departures and arrivals sections.
Eng. Henry Ngobi, the chief engineer at Uganda Civil Aviation Authority-UCAA told the committee member during their oversight visit that at least 79 per cent of the project is complete. He said the project executed by China Communication Construction Company (CCCC) is expected to be completed on May 05th, 2021.