Construction of UGX 18b Processing, Storage Facility Starts in Soroti 3 1

The Shillings 18 billion project comes just months to the completion of Soroti Central Market under the Market and Agricultural Trade Improvement Program Project-2 MATIP-2. The new project is co- funded by the African Development, 82% and Government of Uganda, 18%.
18:24
18:24

Soroti Central Market Works to Delay 1 1 Top story

Moses Otimong, the Soroti Municipal Council Town Clerk, says that much as the contractor, TECHNO 3 Uganda Ltd has completed 95% of the physical works, the finishing might take them up to April due to changes that arose during the monitoring visits by stakeholders.
15:55
15:55

Kitgum Market Workers Strike over Delayed Pay, Poor Working Conditions kitgum main market 1 3

More than 40 workers led a peaceful procession from the market site under construction in central division and pitched camp outside the Resident District Commissioner’s office.