Human Resource Shortage Hurts Kitgum Market Construction Progress kitgum main market 2 1 Top story

Abonga notes that whereas the contractor has registered 50 percent progress in constructing block A and 30 percent progress at Block B, the human resource shortage is likely to affect work.
05:08
05:08

Kitgum Market Construction Suffers Setback Amidst COVID-19 Lockdown 2 1

The construction by China State Construction Engineering Corporation Ltd, which commenced in June last year, has only registered 33 per cent progress, a year since its commissioning. According to the timeline, the contractor was expected to have accomplished 50 per cent of the work by now.