The project has been subject to a number of investigations but nobody has been held responsible for the shoddy work that has compromised a two-trillion shilling dam.
Inspector General of Government (IGG), Beti Kamya
commenced a probe into shoddy work at the 183MW-Isimba hydro power dam.
The IGG’s intervention comes after several years of
demands for accountability by a section of Ugandans.
While it was technically established that the works at
Isimba were far below the requirements of the owner as stipulated in the
contract and as per international standards, nobody has been held liable.
Many have feared that someone might have slept on the job
allowing the Engineering, Procurement, Construction, and Commissioning
contractor (EPCC) to go on with “shoddy” work without proper at such a turnkey
project for Uganda. There is fear that the over two trillion shillings project
$567.7 could go to waste.
The question is whether the government ombudsman will ensure
that someone will be brought to book.
Kamya and her top investigators were at the dam on Friday
amidst concerns that it is at growing risk being washed away by flooding.
It was the second time that the IGG is interacting with
Uganda Electricity Generation Company, officers from the Attorney General’s chambers
and the ministry of energy.
The dam is owned by Uganda Electricity Generation Company
Limited (UEGCL) on behalf of the government of Uganda.
China International Water And Electric Corporation (CIWE) was
contracted to construct the dam sitting along River Nile in Kayunga
District.
Beti Kamya and team toured inside the power house where
the four units of the dam are located.
She was also taken to the spillway. Part of the spillway
is not operational because its integrity was severely compromised by the over
flooding at the facility in August 2022.
Kamya was told that while the dam is producing all the
required 183 MW of power, its spillway is very defective to the extent that it
sends vibrations to the entire structure when the gates are opened beyond 40%.
Electricity
Generation Company Limited (UEGCL) has noted that the spillways structure and
its components are not safe and are unstable based on evidence of concrete damages
and erosion.
Kamya held a closed-door meeting with officials led by
Harrison E. Mutikanga, the UEGCL Chief Executive Officer. Kamya said she was not
impressed by what she and her team had observed from a layperson’s point of
view.
“I can see that there are some quality issues. Especially
with the structure. To me, it looks like a very old structure. Instead of a
structure that is about five years old” she said.
////Cue In “It looks like a ……..
Cue Out.. Investigations”///
The standoff between UEGCL and CIWE.
Beti Kamya noted that while some of the defects have been
observed by the contractor and UEGCL, the two seemed to be what she described
as far apart in appreciating the problem.
“And I think that
is a big problem because you can both agree. Yes we haven’t delivered but we
can deliver.” she said.
///Cue in “They seem to have a…
Cue Out ….needs to be resolved”///
The critical concern at Isimba.
The major point of concern is the quality and standard of
the spillway. A spillway is a waterway used to dispose of
excess flood waterfrom a
reservoir after it has been filled to capacity.
The spillway at Isimba had been designed to evacuate 4,500 Cubic meters (m3) or 4.5
million Liters per second. But currently, UEGCL can discharge less than 40% of
what the dam should have evacuated in case of flooding.
There is fear that the powerhouse at Isimba and related
structures could be swept away in case of an increase in the water levels.
It is further feared the flooding at the dam could
severely impact communities living downstream the river.
Engineer Chad Akita, the UEGCL project manager at Isimba
said the spillway has had a number of challenges starting from June 2022 when a
diving inspection was conducted at the spillway. He said they identified washouts of buffer blocks and
damage to the joints.
“Another inspection was conducted in 2024 by the contractor.
And that inspection confirms that these defects are still existing,” Akita revealed.
“They are still existing, they are increasing from the
evidence collected. These include gaps with in the slab, we have concrete erosion
within the bottom slab. And the main concern here is that the enforcement continues
to be enforced,” he added.
Engineer Chad Akita, told URN that among the requirements
of a spillway is the need to withstand extreme water pressures and the capacity
to manage floodwaters.
“The risks are increasing and we need to take some action
quickly,”
It also emerged that the way the component of the spillway
was designed makes it very difficult to maintain.
The contractor has to higher divers to under the water in
case of maintenance. Two divers died at the spillway after the August 2022
flooding which led to the temporary closure of the dam.
URN learned that there had been attempts to carry out
under water repairs on the spillway but the work was suspended in February
2024, because of increased water discharge on River Nile.
Engineer Harrison
Mutikanga said he always gets sleepless nights because of Isimba dam whenever
it rains.
“Because when you have a spillway that is likely not to
deal with its flood design capacity, and then you are getting a lot of rain,
then you can’t stop worrying. Especially now that the spillway has defects that
compromised its functionality. ,” explained Mutikanga, a civil engineer.
It had been hoped that the contractor would have embarked
on long-term spillway rehabilitation works. There were no such rehabilitation
by the time the IGG was at Isimba.
A UEGCL officials at the site told URN that the
contractor was “dillydallying”.
URN however witnessed men dressed in orange overalls on
top of the powerhouse. Assisted by a yellow crane, the workers were reportedly
repairing leakages on the roof of the power house. At the time of commissioning
in March 2019, Isimba dam had over 700 defects.
These included leakages in the powerhouse roof, cracks in
the powerhouse, internal erosion of the embankment dams, lack of a log boom,
poor cabling in the powerhouse among others.
It is suspected the dam which was constructed using embankment
technology has manifested the persistent defects because of either poor
materials that are not resisting erosion, wear and tear.
Apart erosion and concrete damages at the spillway, it
has also been observed that the water cooling systems at Isimba are not up to
standard.
Experts on site say these could severe consequences,
including reduced operational efficiency, increased maintenance costs, and
potential damage to equipment.
The damages being reported by Electricity Generation
Company Limited were allegedly confirmed China International Water And Electric
Corporation (CIWE) in an December 2024.
UEGCL has indicated that China International
Water And Electric Corporation (CIWE) has been inconsistent with its
presentation of the condition of the dam.
The manager in charge of China International Water And
Electric Corporation (CIWE) at Isimba was not on site at the time Beti Kamya
and her team was visiting.
She was informed that the manager had traveled to
China where had gone to conduct a Physical Model Test (PMT) to determine the
root cause of the structural issues at the third spillway.
The former Energy and Mineral Development Minister,
Engineer Irene Muloni had assigned a team of experts led by a structural
Engineer, Prof. John Senfuma to investigate the shoddy work at Isimba.
The
team had reportedly warned that the dam could burst because the defects. URN
was not able to get access to the detailed report to find out who caused and was responsible for
the mess.
While
at Isimba, Kamya was asked why she was taking interest at the particular moment
and her possible line of investigation into the matter.
The IGG declined to reveal what she and her team is looking for and how it intends to
go about the matter.
She
however indicated that” Wherever there is government interest, the Inspector
General of Government has jurisdiction. Except by law, the office of the
President because it is protected by law. I don’t want to say how far we can
get involved. We want to go and evaluate the information that we have received”
said Kamya.
She
promised to come out with a preliminary position within three weeks.
///Cue In “We look out …….
Cue out …. The problem will be”///
So far, part of the blame has been put Energy Infratech
Pvt Limited (EIPL) an Indian firm contracted by the government to as Owner’s
Engineer or to supervising works at Isimba and Karuma Power Dams.
The then Minister of Energy, Engineer Irene Muloni in
2017acting on President Museveni’s directive suspended EIPL from Karuma and
Isimba dams.
Museveni wrote to Irene Muloni in March 2016, calling for
prompt action against Energy Infratech Pvt Limited (EIPL) after intelligence
reports discovered shoddy work at the two dams.
Energy Infratech Pvt Limited (EIPL)’s contract expired on September 7, 2017, after
a 40 months effective from May 7, 2014.
A project steering team led by Engineer Badiru
Kiggundu in 2017 found that EIPL did not
mobilize experienced key supervision personnel including quality control
specialists, electromechanical specialists and an experienced geotechnical
engineer to fully lead in supervision of construction of the embankment dams, in
spite of repeated recommendation and calls to fill the agreed project
supervision structure.
“This
compromised the construction control aspects and, in some instance, led to non-conformance related to material placement and dam monitoring
instrumentation for both the left and right embankment dams,” Kiggundu explained
in 2017.
According
to Kiggundu, the biggest undoing was the change of materials for electro
mechanical and hydro mechanical equipment.
“Whereas
the EPC contract and employer requirements clearly specified the material
properties for equipment like gates, draft tubes, stop logs, cooling system,
etc, these were changed to materials of lower or inferior grade compared to
what was specified in the contract, under the watch of EIPL" said Kiggundu.
URN
the established that despite the suspension of EPIL’s services, the government continued
to pay it until its contract expired.
The
question is whether the Ministry of energy technical persons looked on while
specifications were altered at a whim, works went shoddy with reckless abandon,
and timelines negated without restraint.