According to the Project Coordinator from KCCA Eng. Stephen Kibuuka, the lock-down was abrupt leaving both KCCA and the contractors without a plan to continue operations immediately.
Culvert Block site on Nakawa Ntinda Road Near Shell Petrol Station
Road construction works in Kampala is set to resume under the Kampala Institutional Infrastructures Development Project two (KIIDP
2) with few workers.
Last year, KCCA started construction of 6km of Kulambiro
Ring to Najeera link, 2km of John Babiiha (Acacia) Road and 3km of
Nakawa-Ntinda road.
Other roads were the 9km of Kabusu-Bunamwaya-Lweza Road in lot two
and 8km of Lukuli-Nanganda Road in lot three.
However, the works stalled when the government imposed a lockdown following the
outbreak of COVID-19.
According to the Project Coordinator from KCCA Eng. Stephen Kibuuka, the
lock-down was abrupt leaving both KCCA and the contractors without a plan to
continue operations immediately.
Kibuuka says they have engaged the Contractors China State Construction
Engineering Company and Sterling to have about 16 workers on each of the
construction sites.
He says these will work on mainly box culverts on John Babiiha Road and Nakawa -Ntinda
Road.
Kibuuka says contractors will provide camps for workers to sleep
at the site. They will be tested and equipped with personal protective gear to
ensure that they are protected from the virus.
Kibuuka says they limited the numbers of workers to avoid crowds.
Samuel Tusasiirwe, the Social Development Officer at CSCEC says that they plan to
resume work by the end of this week. He explains that they have also
worked out an emergency plan on how they intend to safeguard workers against
the Virus.
The 139 billion shillings World Bank-funded project was supposed
to have been completed in 18 months and 15 months for lot one and then lot two
and three respectively. However, it suffered a setback due to the heavy rains
that were experienced last year.
By December, the construction was at 6.2% completion for lot one
while lot two stood at 6.2% and three at 4.76%.
KCCA now estimates that completion could delay for about two
months. It will also require the authority to liaise with the World Bank to
seek an extension of the project.