Construction of the plant followed a bilateral agreement Uganda entered with Tanzania in 2015. However, implementation of the project started in 2017 making it the first cross-border Infrastructure project undertaken by Uganda and Tanzania.
The
Government has switched on the 14 megawatts power plant in Isingiro district with the hope of stabilising the power supply in Ankore and Kigezi regions.
The First Deputy Prime Minister and Minister for the East African Affairs, Rebbeca Alitwala Kadaga commissioned Kikagati-Murongo
Hydro Power Plant that is found on River Kagera along the Uganda Tanzania Borderline
in Kikagati Village, Kikagati Town Council Wednesday.
Construction of the plant followed a bilateral agreement Uganda entered with Tanzania in 2015. However, implementation of the project started in 2017 making
it the first cross-border Infrastructure project undertaken by Uganda and Tanzania.
Speaking at the commissioning exercise, the State
Minister for Energy and Mineral Development, Opolot Okasayi said that the
project will improve the power supply in the region noting that the
government has started constructing a transmission line from Kikaati to Mirama
Hills through to Kabale district to ease the evacuation of the electricity generated.
//Cue in:
“This project will…
Cue out:
…supply in Mbarara.”//
He said through the Uganda Electricity Transmission Company
Limited, the government has signed an agreement with Tanzania Electricity Supply Company and the
power generators Berkley Energy to purchase the power generated at the plant and
equally share it equally with each country getting 7 megawatts.
//Cue in:
“In the bilateral…
Cue out:
…electricity supply company.”//
He said that
in the agreement Uganda Electricity Transmission Company Limited shall be the
lead power purchaser at a leveled Generation Tariff of US Cents 8.5 per unit,
which is about 320 Uganda Shillings, making it the cheapest in the country.
//Cue in:
“in light of…
Cue out:
…per kilowatt hour.”//
Julius
Wandera, the Cooperate Affairs Manager Electricity Regulatory Authority, says that the power plant was added to the national grid in
February this year when it started generating power commercially. He said they are still waiting for Tanzania side to complete its transmission lines.
//Cue in:
“This is a…
Cue out: …to
be completed.”//
The First Deputy Prime Minister and Minister for East African Affairs, Rebbeca Alitwala Kadaga said that the government
had returned the power plant that was destroyed during
the liberation war in 1979.
//Cue in: “The
government has…
Cue out: …day
to celebrate.”//
She said
that the power plant was commissioned at the right time when the government is
rolling out the parish development model that aims at value addition and challenged the local communities to set up industries that will add value to their agricultural
products.
//Cue in:
“it has come…
Cue out:
…shelves in Kampala.”//
The Project General Manager, Daniel
Theron said that they exclusively financed the Construction of the plant at US 100 Million dollars about
380 Billion Ugandan Shillings. Its commissioning has now increased Uganda’s
power generation capacity to 1184 Megawatts from 1,177Megawatts.