The harsh weather conditions that hit Kigezi sub-region have slowed the ongoing construction of Kabale Modern Central Market.
The Construction of the 23 billion Shillings facility by the
Chinese Chong Chuing International Construction Company started in December
2019 under the World Bank-funded Markets and Agricultural Trade Improvement program – MATIP III. It is expected to be complete by December 2021. The market will comprise 859 lockup shops, 676 stalls, a medical clinic, a Daycare Centre,
and restaurants, among others.
However, Charles Muguya, the project site engineer says that
the progress of construction now stands at 37 per cent compared to the time
the frame of 41 per cent. Muguya says that
the 4 per cent behind the timeframe is caused by heavy rains that disrupted workers
while on duty.
//Cue in; “per now the…
Cue out…so far.”//
Hilary Tugeineyo, the Clerk of Works from Sileshi Consult,
an Engineering Company supervising the project says that rains have hampered the delivery of materials especially sand which is picked from places where
roads were damaged by running waters and landslides.
Tugeineyo adds that the recent closure of
Kabale-Ntungamo road after it was damaged by landslides affected
the supply of Cement from Kasese. Tugeineyo
says that as a result, the roofing of Block A, Block B and Block A-Annex Block C is behind schedule.
//Cue in; we also had…
Cue out…this project.”//
Rukiga
//Cue in; “twahisa ebichweeka 37…
Cue out: …munonga enjura.”//
Emmanuel Sentaro Byamugisha, the Kabale Municipality Mayor says
that even though the contractor is behind the schedule, he is still on track.