The ruling was on miscellaneous cause 24 of 2023 filed by the Attorney General versus 42 respondents. The suit was filed as per Article 26(2) of the constitution and under the Land Acquisition Act and Civil Procedure Act among others.
Landowners to be displaced by the oil and gas
projects in Hoima and Buliisa Districts suffered a major setback on Friday
after a judge allowed the government to deposit their compensation money to the
Court. Justice Byaruhanga JesseRugyema ruled that those with grievances
should appeal.
The ruling was on miscellaneous cause 24 of 2023
filed by the Attorney General versus 42 respondents. The suit was filed as per
Article 26(2) of the constitution and under the Land Acquisition Act and Civil Procedure
Act among others.
The 42 landowners had refused compensation rates
offered by the government for them to relocate and allow the development of oil
infrastructure under the Tilenga project by TotalEnergies.
Hoima High Court udge,
Byaruhanga JesseRugyema
ruled in favor of the Ministry of Energy represented by the Attorney General that
over 950 million shillings should be deposited at the court.
The ruling means that the government can now evict the
landowners, and allow the projects to go on. The landowners refused the compensation
rates approved by the government Chief Valuer saying they were low and unfair. The land in dispute is close to 60 acres in Hoima
and Buliisa districts.
Lawyers representing the landowners or project-affected
persons had tried to ask the Judge to postpone the ruling saying some of the
sued persons were not in the court. The judge briefly adjourned to allow the lawyers
from the Attorney General’s chambers and the respondents' lawyers to consult.
The two sides did not agree when they
returned to court. Ten of the respondents were represented by a lawyer.
Mugisa Jealousy Mulimba, one of the project-affected
persons told URN that they will consult their lawyers over the possibility of appealing
against the ruling.
He said the judge hurriedly considered the matter without
giving the respondents to chance to be represented by lawyers.
The legal battle stemmed from a suit filed by the
Attorney General on 4th December against the 42 Projects Affected
Persons from several villages in Buliisa and Hoima Districts.
The Ministry of
Energy Permanent Secretary, Irene Bateebe swore an affidavit which was relied
on to hear the application. It among other issues said the government through
the Government Chief Valuer carried out a valuation of the projected affected land
and that the valuation for each Resettlement Action Plan (RAPS) was approved by
the Government Chief Valuer to facilitate Compensation for the affected
persons.
That following disclosure of compensation entitlements,
Mugisa Jealousy Mulimba, and 15 others rejected compensation amounts as assed
by the project approved by the Government Chief Valuer, and some of the
respondents had ownership and disputes over part of the land required for
project activities which the government had no mandate to decide or resolve or
decide who the rightful owner of the land is.
She further stated that since March 2021, the
government has been unable to pay compensation to some of the respondents because
they cannot be traced despite several attempts to locate them including
community drives, consultation with local leaders, known neighbors, relatives,
and radio announcements.
Bateebe particularly singled out Fred Balikenda from
Kirama Village, Kigwera Sub-county whom she said despite receiving compensation
and having several engagements with the government refused to vacate the land.
On 18th September, the government Chief
Valuer who had been appointed as the Assessment Officer for the Tilenga project
published a notice of intention by the government to take possession of the land
in dispute. The respondents were given 30 days within which to submit their
claims.
The respondents were reportedly served with notices inviting them to
meetings but most did not turn to the meetings.
She said the
refusal by some of the respondents to accept compensation rates, and the
failure by some to resolve ownership wrangles greatly constrained the implementation
of the Tilenga Project to the detriment of the country’s oil and gas sector.
She further stated that in the interest of Justice,
the ministry should be granted leave to deposit the respondents' compensation
money in court and an eviction order against Fred Balikenda to enable the implementation
of the Tilenga project.
The Court allowed Balikenda should be evicted so
that he could move to the house constructed for him by TotalEnergies. Balikenda
is still defiant even after the court ruling. “I was not satisfied with the
judgment. This is what I can tell you. I need AFIEGO to help me in this matter.
All the NGOs. I need them to come and help me. Because with me I cannot afford
the legal costs” he said
////Cue In “Me as you know ....
Cue Out...which they constructed"////
Seremos Kamuturaki another respondent told URN that
he was equally not happy with the ruling.
“Many of us have not agreed with the decision that
the money should be deposited to the court accounts. However the judge ruled
that the money should be put on the account. So we have remained not satisfied.
So we feel that we should have another
step”
AFIEGO Chief Executive Officer Dickens Kamugisha
said what the government has done is contrary to Article 26 of the 1995
constitution.
Under
Article 26 (2) (b) of the Constitution, compulsory
acquisition of property can only be made under a law that makes provision for
prompt payment of fair and adequate compensation prior to the taking of
possession.
He
said they plan to appeal against the ruling though he expressed doubt whether
the court will move as fast as it did while disposing of the application by the
attorney general.
The court has previously ruled in the Uganda
National Roads Authority Vs. Irumba Asumani & Peter Magelah, Supreme Court
Constitutional Appeal No.2 of 2014. The Supreme Court confirmed the sanctity of
property rights under the Constitution.
Article 26 of
the Constitution on freedom from deprivation of property provides for prompt
payment of fair and adequate compensation prior to the State’s compulsory
acquisition of any property.
The Court ruled that the Land Acquisition Act (Cap
226) is unconstitutional in so far as it provided for the compulsory
acquisition of property before the payment of compensation to the owner.
UNRA appealed to the Supreme Court and sought to
argue, among others, that Article 26 was not a non-derogable right and that in
certain circumstances, the State would be entitled to compulsorily acquire
property before payment of compensation for instance in situations of natural disasters,
emergencies or in the interest of public good.
The Supreme Court upheld the Constitutional Court
decision that the Land
Acquisition Act was inconsistent with Article 26 of
the Constitution and therefore unconstitutional.
“What they are
doing is total impunity and abuse of the court process. They have used the
court to chase Balikenda from his land contrary to the constitution,” said
Kamugisha.
Kamugisha told URN in an interview that the Court
did not grant the applicants 14 days to enable them to file their defense. He said
they had information that TotalEnergies had threatened to take action against
the government for failure to ensure vacant possession of the land to enable it
to proceed with work.
The ruling could be used to ensure that absentee landlords whom the EACOP project has failed to trace could equally have their money deposited with the court for work on crude oil pipeline to go on .