Construction of the community dam situated in Paicam Parish, Otaka watershed, kicked off in February this year after the government through Office of the Prime Minister-OPM disbursed 132 millionn shillings.
IMG-20211026-WA0015
Residents
of Paicam Parish, Lamiyo Sub County in
Agago district have accused their Community Project Management Committees
(CPMCs) of mismanaging funds meant for the completion of Acuku Community Dam
Project under the Northern Uganda Social Action Fund phase three (NUSAF III).
Construction of the community dam located in Paicam Parish, Otaka watershed,
kicked off in February this year after the Office of the Prime Minister-OPM
disbursed 132 Million Shillings.
It is meant to provide sufficient water for boosting livestock production in
the area and improved household income for 53 selected group members in the
community.
The group members however say the dam project which was to be completed by July
this year suffered delays following corruption allegations by executive members.
For instance, members alleged that shillings 15.7 million meant for
Environmental Conservation management, and HIV /AIDs awareness training among
the Communities were not paid to the beneficiaries.
Irene Oyella, one of the group members notes that the contractor, Geneber Enterprise
Limited contracted to undertake the dam construction failed to install culverts
on an access road at the dam site.
She notes that members of the group were also supposed to receive a total of
shillings 26 million as payment for labour but only 18 million shillings was
paid out to the beneficiaries.
“It is not fair to divert community benefits for personal gain. The Bill of
Quantity was not presented to the group at the start of the project, members
were paid only shillings 18 Million out of 26 Million shillings stated in the
BOQ and that has made members so aggrieved on the decision of the executives,”
she said.
Johnson Otim, the LCll Chairperson of Paicam Parish says only 50 percent of the
project work has been completed adding that the site has since been abandoned
by the contractor who was paid shillings 92.6 million.
He notes that the site engineer during the execution of work forged letters
requesting for the release of the fund minus informing group members, which
violated the guidelines in NUSAF3 implementation.
According to the project bill of quantity (BOQ), out of the shillings 132
million, 70 percent of the project fund was to carter for Equipment, 20perceny
for Labour, Four percent on Environment management and HIV/Aids while CPMC
Administrative cost was at two percent and BOQ design at four percent.
Otim says the group currently has only Shillings 5.5 Million Shillings in their
bank account which was raised under the Village Saving and Loan
Association-VSLA.
But
David Komakech, the Chairperson for the Community Project Management Committee
who is being accused refuted the allegations of mismanaging the project
fund.
He says the allegations are political and arise out of hate from a few members.
Suzan Akany, the Agago Resident District Commissioner says she has received
complaints from the aggrieved members adding that she will follow up on the
matter.
The group members have since opened up a case of fund mismanagement against
their executive members, David Komakech, Okello Titus the group secretary,
Treasurer Dorothy Ayaa, Site engineer Raymond Olyel and the Facilitator Juma
Muhammad at Patongo Central Police Station (CPS) under CRB 27/9/2021.
NUSAF phase III project ended on June 30 this year. The project became
effective in March 2016 and was implemented through the Office of the Prime
Minister with funding from the World Bank to provide effective income support
and build the resilience of poor and vulnerable households in Northern
Uganda.
The project comprised of four components; labour-intensive public works (LIPW)
and disaster risk financing, livelihood investment support, strengthening
transparency, accountability, and anti-corruption (TAAC) and safety net
mechanisms and project management.
Bureau Chief, West Acholi