Warning: Trying to access array offset on value of type bool in /usr/www/users/urnnet/a/story.php on line 43 Pader Officials Accused of Approving Substandard Works :: Uganda Radionetwork
The projects include the construction of 89 million shillings Outpatient Department block at Amilobo Health Center III in 2016/2017 financial year and 12 million shillings teachers house construction at Amilobo primary school in 2018/2019 financial year.
Pader district officials have come under criticism for issuing
certificates of completion for substandard projects.
The accusations stem from two buildings that were poorly constructed
in the financial years 2016/2017 and 2018/2019 at a tune of 181 million
shillings. They include the 89 Million Shillings Outpatient
Department block at Amilobo Health Center III and
12 million shillings teachers’ house at Amilobo primary school.
The other is the 80 Million Shillings construction of toilet stances
at Amilobo Primary School all undertaken by Ajalo Co. Ltd, a local contractor
in the district.
Laguti Sub-County LCV Councilor, John Chris Anywar Mugisha says that the
certificates of completion were issued even after several complaints to the
district officials.
Anywar alleges that Ajalo Co. Ltd which was contracted for all the projects
belongs to a civil servant in the district adding that award of the contract to
the contractor is questionable due to their competency level.
Laguti Sub-County Chairperson Christopher Odokonyero says most of
the local government infrastructural projects in the sub-county have been
issued certificates of completion authorizing payment to the contractor over
shoddy works.
He singled out the construction works on Amilobo Health Center III
outpatient department and Tumalyec Teachers quarters which were not supposed to
start operations due to the shoddy works.
Luo
//Cue in: “calo ot yat…
Cue out:…tuki ao weng.”//
Pader District Engineer, Benedict Lubang however denied the
allegations of issuing out certificates of completion to sub-standard
structures.
Lubang says all the local government projects are monitored and
guided by the district works committee and other technocrats adding that
issuance of certificates is only done after quality assurance.
//cue in: “ka ki timo...
Cue out:…no pe ber.”//
Simon Peter Otto, the Director Ajalo Co. Ltd acknowledges that
they had some gaps during the construction of Tumalyec Primary School but notes
that the defects were fixed.
He says they were rightly awarded certificates of completion for
the projects undertaken after the district officials accompanied by the
engineer and sub-county leaders made inspections to the project sites.
Otto however says they can’t take the blame for shoddy works on projects
undertaken in the financial year 201/2017 since they were only contracted to do
finishing after two contractors abandoned the site.